    Current Status
   
 

Milestone

Status

Contract for Design & Development

Awarded

Topographic Survey

Completed

Land Utilization Plan

Approved

Project Master Plan Approval from Port Qasim Authority

Approved

Leveling & Grading Works

Completed

L.O.I. for 250 MW Captive Power Plant for Textile City

Issued

Gas Connection by S.S.G.C.

Approved

Environment Impact Assessment (EIA) Report by E.P.A. Govt. of Sindh

Approved

Laying of 23 km, 48 inch dia Water Supply Pipeline by KW&SB to Textile City

20% Completed

Construction of Water Works Package (20 MG Reservoir, Filtration Plant and Overhead Tank)

Started

Design for Combined Effluent Treatment Plant (18 MGD) by M/s NEC

Finalized

Work on Priority Road Package (50 m and 100 m wide R.O.W.)

60% Completed

Construction of Admin Building at site

90% Completed

Commencement of sale of industrial plots

Soon

Completion of project

2012