|
Milestone |
Status |
|
Contract for Design & Development |
Awarded |
|
Topographic Survey |
Completed |
|
Land Utilization Plan |
Approved |
|
Project Master Plan Approval from Port Qasim Authority |
Approved |
|
Leveling & Grading Works |
Completed |
|
L.O.I. for 250 MW Captive Power Plant for Textile City |
Issued |
|
Gas Connection by S.S.G.C. |
Approved |
|
Environment Impact Assessment (EIA) Report by E.P.A.
Govt. of Sindh |
Approved |
|
Laying of 23 km, 48 inch dia Water Supply Pipeline by
KW&SB to Textile City |
20% Completed |
|
Construction of Water Works Package (20 MG Reservoir,
Filtration Plant and Overhead Tank) |
Started |
|
Design for Combined Effluent Treatment Plant (18 MGD) by
M/s NEC |
Finalized |
|
Work on Priority Road Package (50 m and 100 m wide R.O.W.) |
60% Completed |
|
Construction of Admin Building at site |
90% Completed |
|
Commencement of sale of industrial plots |
Soon |
|
Completion of project |
2012 |